Loading…

| Date | Type | Details |
|---|---|---|
| 23 Sep 2024 | Mechanical Fault | Delayed in returning to Ardrossan-Brodick service due to an issue with its port-side gearbox. Operators confirmed the vessel would remain out of service for at least another 10 days as of 02 Oct 2024. |
| 11 Feb 2024 | Other | Ferry arrived at Cammel Laird in Birkenhead for an extensive assessment of the required repairs. CalMac confirmed that the the vessel will be out of service for a further four months due to structural strengthening and steelwork issues, as a large area of severely corroded and weakened steel was discovered in an awkward location beneath the engines. |
| 09 Nov 2023 | Mechanical Fault | Ferry had steering issues in Ardrossan, UK. LOCH FYNE replaced her on shuttles between Claonaig and Lochranza. Repairs were carried out and resumed service on 12 November. |
| 02 Sep 2023 | Mechanical Fault | Ferry had main engine failure and sailings between Ardrossan and Brodick, UK were delayed and even cancelled. Sailing resumed after repairs. |
| 06 Jan 2023 | Other | Vessel was taken out of service for its annual overhaul and had been in dry dock, in Greenock, UK, with more than £1M of work being done, including engine servicing. She returned to service on 18 April. |
| 06 Aug 2022 | Mechanical Fault | Vessel missed a sailing due to a technical issue on the island's busiest day of the year. Police had to be called to Ardrossan port to calm passengers down as well at Mallaig. |
| 06 Aug 2021 | Medical Emergency | Vessel itinerary cancelled after crew member tested positive with Covid-19. Replacement ferry used as a temporary backup. |